SAP S/4HANA Finance FAQ: Real-Time Posting and Period-End Close
SAP Controlling Conference attendees participating in a presentation

Search Posts

Which SAP S/4HANA Finance processes post during the period, and which still run at close? Janet Salmon answered questions about planning, overhead, allocations, production accounting, and Material Ledger after a June 2017 webinar she presented with Birgit Oettinger.

Janet Salmon
Janet Salmon, webinar co-presenter and FAQ author.

Janet’s original answers are summarized below. The ERPCorp updates identify where the process can differ in newer releases. Check your edition, release, and configuration before applying a posting or closing procedure.

Does financial planning use ACDOCA or ACDOCP?

2017 answer: Plan data goes to ACDOCP. When copying actuals to a forecast, choose whether to copy at the original level of detail or aggregate the data. Twelve forecast versions don’t automatically mean twelve copies of every actual line item.

ERPCorp update: ACDOCA stores actual journal entries, and ACDOCP is the main table for financial planning in SAP S/4HANA Cloud Public Edition. Check the dimensions and level of detail required by your reports before deciding how to aggregate the forecast. See SAP Help’s financial planning architecture.

Does costing sheet overhead still run at month-end?

2017 answer: Janet described an option for overhead to post with each qualifying transaction using the CO_ALLOCATIONS business function. She contrasted it with cumulative month-end overhead such as the process discussed in the CO43 question.

ERPCorp update: In supported scenarios, event-based overhead can post alongside the originating transaction when the costing sheet is configured for it. Periodic calculation uses the actual costs of the object for the selected period. See SAP Help’s event-based overhead documentation.

Can assessments and distributions happen in real time?

2017 answer: SAP can derive certain profitability characteristics at posting time when the required source data is available. An assessment that creates multiple receiver lines still needs a separate allocation process. For the audience example of moving 100% from business area A000 to I000, Janet distinguished enriching an original line from distributing costs through a cycle.

ERPCorp update: Use derivation to populate reporting dimensions on a line and an allocation cycle to redistribute costs according to sender and receiver rules. If a percentage changes, check the original run and the applicable reversal and rerun process before posting again. See SAP Help’s Run Allocations documentation.

When do WIP, variances, and settlement post?

2017 answer: Work in process (WIP) and variance calculation were month-end activities in the SAP S/4HANA 1610 scenario discussed. For settlement, Janet explained that profitability characteristics could sometimes be derived earlier from a settlement rule or sales order item.

ERPCorp update: Event-Based Production Cost Posting can calculate and settle WIP and order balances for supported manufacturing scenarios. Other configurations can still require periodic or manual processing. Deriving a profitability characteristic early does not itself settle the order. See SAP Help’s guide to WIP, variances, and settlement.

What is Prima Nota?

2017 answer: Prima Nota is the original document that records a business transaction. Examples include a time confirmation or material movement. It describes the document’s role in the transaction, rather than a particular SAP document type.

Does Material Ledger run in real time or at month-end?

2017 answer: Goods movements can be valued at standard cost during the period. Actual Costing is periodic, so later postings such as supplier invoice differences can be included when the actual price is calculated.

ERPCorp update: With Actual Costing active, a period-end run can calculate a periodic unit price and use it to revalue inventory, depending on the closing settings. See SAP Help’s Edit Actual Costing Runs documentation.

For the companion overview, read Birgit Oettinger’s guide to real-time posting in SAP S/4HANA Finance.